How to Calculate Takt Time on a Chain Conveyor Assembly Line
Takt time is the starting point of assembly line design: takt = available working time / planned output. On a motor assembly line, for example, 450 minutes of available time per shift and 450 planned units give a takt of 1 minute per unit.
Station count works backwards from the takt: divide each operation's standard time by the takt and round up, then add up for the minimum station count; allow an 85–90% loading buffer to get the actual station count and line length.
When laying out stations, split or parallel the bottleneck operation instead of letting one station cap the whole line; pallet size, stopper spacing and lift-and-transfer losses also belong in the line balance calculation.